Witches Oak Water Treatment Works
65 million
litres per day will serve a population equivalent of 400,000 consumers
£130 million
design and construction contract
£566 million
Green Recovery Programme
150
people on-site
Project summary
MWH Treatment is the principal contractor and designer for Severn Trent Water’s state-of-the-art Witches Oak Water Treatment Works in Derbyshire, drawing on the company’s specific skills across design, engineering, procurement, construction and commissioning. MWH Treatment was also able to incorporate its recent design and construction experience with Severn Trent Water’s Church Wilne granular activated carbon plant.
The background
The project is part of Severn Trent Water’s £566 million Green Recovery Programme, and the treatment works will provide an additional average flow of 65 million litres per day and increase resilience of the Derwent Valley Aqueduct (DVA) network, which supplies the East Midlands grid.
The new Witches Oak Water Treatment Works comprises the following main processes:
- Balance tanks with booster pumps
- Strainers
- Enhanced coagulation
- Ceramic membranes
- Granular activated carbon
- UV and chemical disinfection
- Treated water tank
- High lifting pumping station
- Emergency return pumping station
- Administration building with control room, laboratory, welfare facilities, offices and workshop
- Associated chemical bulk storage and dosing
- Associated backwash and sludge handling
- High-voltage substation with ring main and seven low-voltage process motor control centres with SCADA
- Security and Emergency Measures Direction (SEMD) security system with 15 CCTVs and perimeter fencing
In addition to MWH Treatment, RSK Group has been able to offer Severn Trent Water the multidisciplinary services of additional RSK companies. These include Stephenson Halliday (landscape appraisal), ADAS (soil surveys), Hollywood Civil Engineering (high-voltage substation and backwash buried pipework), LDE (specialist surveys), CR Civil Engineering
(civil works), Elsym (electrical installation) and Cognica (operations and maintenance manuals).
The challenges
Owing to the water quality challenges in treating the River Trent and the new technologies being implemented, Severn Trent Water conducted a comprehensive series of pilot trials, which provided invaluable data to confirm the basis of design and operating parameters. A second pilot plant is now treating the Derwent raw water so that the commissioning parameters can be confirmed based on seasonal variations throughout 2024.
As a result, the process designers have introduced two raw water balance tanks to the project. This will allow blending, storage and control of the flow from the abstractions at Witches Oak lakes and River Derwent upstream of the in-line coagulation and adsorption (ILCA).
The solutions
MWH Treatment has utilised digital delivery tools, including digital surveying, interactive visualisations, intelligent 3D models, 4D rehearsals and digital inspection and test plan field management as part of this project. In the hands of experienced engineers, these tools enable much greater project efficiency, with 3D elevating the design process and allowing construction sequencing and overlapping of site activities to optimise the schedule and reduce build time.
The ability to view the project in such intricate detail, effectively seeing inside the 3D model for the treatment works, offers real game-changing opportunities for project management. It becomes a truly interactive experience and one in which we can engage all our supply chain partners. With multiple teams carrying out work across the site, being able to visualise who is working where and the challenges and opportunities this can create is a considerable step up from the 2D drawings of the past. This enhances the health and safety of the site team by improving communication and reducing risks.
A £7.4 million saving was achieved by identifying the opportunity to use existing capacity for sludge management at Derby Sewage Works rather than providing sludge dewatering at Witches Oak. A further £1.6 million saving was generated through a whole life cost appraisal of an OSEC system versus sodium hypochlorite. This value engineering has funded additional scope that has improved process resilience on the new plant and been used to mitigate project risks.
The impact
A fast-track scheme of such complexity requires the highest level of collaboration among stakeholders, design engineering disciplines, constructors and supply chain partners. At peak, there were 150 people on-site, working together to the highest quality and health and safety standards. The programme was extremely detailed and had to be broken down into manageable lookaheads, which were reviewed weekly in collaborative planning sessions.
The site management team utilised trackers for the pipework to monitor and control progress. The project engineers conducted expediting visits to the key suppliers to verify that manufacture was on schedule. Working at such a fast pace required constant problem solving, timely decision-making and adaptability to maintain progress. We had to employ multiple civil and mechanical, electrical, instrumentation, control and automation (MEICA) installation teams to secure the required resources for concurrent working at the busiest period of the AMP; this had the added benefit of healthy competition on-site. The commissioning team developed a detailed seven-stage plan to test and commission all the new assets and achieve water into supply. This was digitised into a 16-minute animation, which helped the new operators visualise the process to understand the sequence and constraints. To design, build, assemble and commission an entire new water treatment plant in two-and-a-half years is a real achievement and leaves a legacy for the local community in which the whole team should be immensely proud.
Featured businesses
MWH Treatment
Joining the RSK Group in 2021 and based in the Manchester area in the UK, MWH Treatment is a sector-leading solutions provider operating across the UK water industry, with over 800 process intelligence professionals and a sector heritage that dates back to 1820. Today, the water sector is facing unprecedented challenges that are driving the need to find smarter ways to achieve sustainable outcomes.
Learn more about MWH TreatmentStephenson Halliday
Established in 2001 and operating across the UK and Ireland, Stephenson Halliday provides environmental planning and landscape architecture services.
Learn more about Stephenson HallidayADAS
ADAS is the UK’s largest independent provider of agricultural and environmental consultancy, rural development services, research and development and policy advice. It has more than 75 years’ experience of delivering national agricultural and environmental consultancy services that tackle two major issues of modern times: securing the food supply and enhancing the environment. ADAS works alongside farmers, landowners, corporate organisations and the government to help them achieve their sustainability goals.
Learn more about ADASHollywood Civil Engineering
Established in 2008 and based in Willenhall in the West Midlands, Hollywood Civil Engineering operates nationally and provides mechanical installation, formwork and infrastructure, with an emphasis on managing and executing turnkey projects from start to finish.
Learn more about Hollywood Civil EngineeringRSK Land and Development Engineering (RSK LDE)
RSK Land and Development Engineering (RSK LDE), formed in 2003 and based in Wigan, Coventry and Hemel Hempstead in the UK, is a leading integrated environmental, engineering and technical services business providing multidisciplinary solutions to a wide range of clients within the private and public sectors.
Learn more about RSK Land and Development Engineering (RSK LDE)CR Civil Engineering
CR Civil Engineering was founded in 2000 as a team of five and has grown significantly since to now employ more than 235 direct staff and 50 contractors. The business is headquartered in Loughborough, UK, and has other offices in Llandeilo, Rotherham and Ripley.
Learn more about CR Civil EngineeringElsym Installations Limited
Elsym Installations, based in Burton-on-Trent in the UK and formed in 2000, is an established electrical contractor with vast experience working in the production and process side of a wide array of industries.
Learn more about Elsym Installations LimitedCognica
Cognica, formed in 1998, is a UK‑based digital engineering and data consultancy specialising in asset information and digital transformation for infrastructure‑intensive organisations. Headquartered in Swindon, it supports clients nationally and internationally and operates primarily within regulated and asset‑heavy sectors, including construction, transport, utilities, energy, water and local government.
Learn more about Cognica