Ask us a question

    CAN-doing Ashley Hill

    The Filton Bank Four Track project is one of Network Rail’s flagship projects and is, according to reports, essential to “unlocking the potential of the wider network to deliver the new Intercity Express Programme”. The project, located in a highly constrained urban environment, runs for 6 km through Bristol city centre. The project aims to remove a significant bottleneck in Bristol by increasing the number of tracks from two to four between Dr Days Junction and Filton Abbey Wood Station.

    Geotechnical specialists CAN completed several cutting and embankment earthworks projects to facilitate an increase in the width of the trackbed over the scheme length. In the 1980s, two of the original four rail tracks had been removed, but major improvements were needed to restore 15 km of twin track, including signalling, track bed and infrastructure work.

    Ashley Hill south embankment is 300 m in length with properties restricting access to the toe. The proposed new track alignment extended beyond the crest line. So, engineers sought to widen the crest of the embankment with a retaining wall and to reinforce the slope below with soil nails and a TECCO netting facing.

    CAN’s working area involved navigating a narrow access track along the crest of the cutting, which demanded a complex programme of works to take account of the limited space and inability to transport large machinery to the worksite. The adjacent live rail lines added additional complexity, thus requiring much of the pile driving to be completed during the night.

    CAN engineers installed more than 1400 soil nails (up to 20.5 m long) in difficult mixed ground conditions along the embankment using A-frame drill rigs on the slope and underreaching excavator-mounted drill rigs from the crest. Up to six drill rigs were operating concurrently, working efficiently in a carefully planned sequence.

    The retaining wall consisted of 178 steel H-section driven piles up to 7.5 m long, installed to extremely tight tolerances by CAN’s specialist subcontractor SPI Piling. Several 8-ft raking soil nails were drilled through the waling beams and clearance holes in the concrete planks to provide additional restraint against overturning.

    Despite the difficulty in access and logistics, CAN completed its programme on time, on budget and to stringent quality standards.

    • Location: United Kingdom
    • Project status: Complete
    • Clear filters
    Found 212 Results
    Page 1 of 18
    Supporting the creation of a new garden village in Cheshire
    View Project
    Repairing lightning damage on a wind turbine in Scotland
    View Project
    Helping Singapore meet its future waste disposal needs
    View Project
    Designing and assessing an onshore wind farm in the Highlands of Scotland
    View Project
    Designing and assessing proposed windfarms in Scotland
    View Project
    Environmental and social risk appraisal support for African “power-to-x” development
    View Project
    Consulting on the construction of the Keppel Marina East Desalination Plant, Singapore
    View Project
    Bringing international best practice and process to phase 2 of Singapore’s Deep Tunnel Sewerage System
    View Project
    Facilitating renewable energy investments in Europe
    View Project
    Ensuring shale gas projects for Poland and beyond
    View Project
    Providing award-winning storm water solutions for urban flooding challenges
    View Project
    Upgrading sewage treatment facilities to serve community needs in Hong Kong
    View Project

    😮 80% of all brownfield development sites in the UK are impacted with asbestos in the soil or made ground at some level.

    📌Join us on this webinar that will outline some of the major issues involved in the control of asbestos in made ground in site development, the potential impacts on options appraisal and techniques that can be used to minimise issues arising from these.

    𝗦𝗽𝗲𝗮𝗸𝗲𝗿: Toby Gibbons, Operations Director of RSK Asbestos
    𝗠𝗼𝗱𝗲𝗿𝗮𝘁𝗼𝗿: Melissa Fox, Managing Director of RSK Asbestos

    Register now in our bio!

    #RSKevents #asbestos #sitedevelopment #development #construction #engineering #brownfielddevelopment
    ...

    🍃 To respond to the ongoing climate crisis, we need more renewable energy.

    🌎 Recent global events have further highlighted the urgency of a smoother transition to net zero.

    ✔️ In this edition of our series Climate Realities, RSK Renewable Energy Director Mike Kelly explores the opportunity for offshore wind to contribute significantly to the UK’s response to the climate crisis and national energy demand.

    Read more in our bio!

    #RSKGroup #climatechange #climatecrisis #sustainability #environment #environmental #renewables #renewableenergy
    ...

    📸 #selfiesonsite 🤳

    RSK Staff had an amazing time attending the Tameside Careers and Apprenticeship Exhibition!

    Want to join our team? View our latest opportunities 👉 www.rskgroup.com/careers

    #RSKgroup #behindthescenes #meettheteam #RSKfamily #RSKonsite #education #careers #careerfair #apprenticeship
    ...

    🌳 How can businesses improve their relationship with nature?

    📌 Join Dr Rossa Donovan, Technical Director at Nature Positive, on a webinar that will explore how well the business community understands its dependencies and impacts on nature and how that translates into corporate strategies.

    Find out more and register now in our bio!

    #RSKEvents #RSKGroup #RSKfamily #nature #business #sustainability #environment #environmental
    ...

    📸 #selfiesonsite 🤳

    RSK Tanzania has been out completing a reconnaissance field study for a proposed solar farm at Kilambo village in Iringa.

    Want to join our team? View our latest opportunities 👉 www.rskgroup.com/careers

    #RSKgroup #behindthescenes #meettheteam #RSKfamily #RSKonsite #construction #careers
    ...

    Copy link
    Powered by Social Snap